"Also, a point to anyone who wishes to supply printed material (all be it scanned), what is the copyright of the document?
On this forum we have fantastically intelligent people who make a living from publishing great books and guides that we all use, by scanning and copying we are depriving that author of their rightful payment.
So, if you are not the author or rightful owner of the works or you do not have the specific permission of that entity to copy their works, please do not do it.
We will not condone copyright theft."
Regards
Mark
Member for
17 years 8 months
Member for17 years8 months
Submitted by Shahzad Ahmad on Wed, 2009-04-08 00:06
Member for
17 years 5 monthsRE: Current Project finish date And Baseline finish are sa
Gents
Please look at the following thread;
http://www.planningplanet.com/forum/forum_post.asp?fid=1&Cat=9&Top=48465
Particularly & I quote from Davids post;
"Also, a point to anyone who wishes to supply printed material (all be it scanned), what is the copyright of the document?
On this forum we have fantastically intelligent people who make a living from publishing great books and guides that we all use, by scanning and copying we are depriving that author of their rightful payment.
So, if you are not the author or rightful owner of the works or you do not have the specific permission of that entity to copy their works, please do not do it.
We will not condone copyright theft."
Regards
Mark
Member for
17 years 8 monthsRE: Current Project finish date And Baseline finish are sa
Hi-All
Training Manual Is a Hrad Binder Books.
I will try to scan it then i can send to all of You.
Thanks
shahzad
Member for
17 years 3 monthsRE: Current Project finish date And Baseline finish are sa
Hi Shahzad
can you please send to me the training manual my e-mail abeer3mt@hotmail.com
Thanks for your help.
Abeer
Member for
18 years 3 monthsRE: Current Project finish date And Baseline finish are sa
hi shahzad
can you share to me the training manual
pinantoot@gmail.com
thank you
Member for
17 years 8 monthsRE: Current Project finish date And Baseline finish are sa
Thanks , Mr Puy.
My explanation was not clear ..it was my main problem.
again Thanks.
I would like share my Training Manual which is full of example solving prob..etc..
Thanks so much for Your advice.
Regards
Shahzad
Member for
17 years 8 monthsRE: Current Project finish date And Baseline finish are sa
Hi Mr. Puy
i create a copy of my master Schedule before update that
Basline -B1 which listed in my based Maintain base line Tab.
Ans. of your question yes i know how to save a copy thru Maintain basline / restored etc.
my problem has been solved with my training Manual.
In the manual
Member for
18 years 6 monthsRE: Current Project finish date And Baseline finish are sa
Hi Shahzad,
If I understood you, your project & primary baseline is your current schedule. Therefore, your current & baseline schedule are the same.
Your current programme should came from the baseline programme and being updated weekly or monthly depending on your contract requirements.
My question is, do you know how to maintain & assign baseline? If not, then here are the steps:
1. Create a copy of your Approved Baseline Programme.
2. After creating, go to Project Menu --> Maintain Baseline then select "ADD".
3. Tick the "Convert another project to a new baseline of the current project" then OK.
4. Select the newly created copy of your Approved Baseline and assign & close.
5. Go to Project Menu --> Assign Baselines, and assign the added Approved Baseline to "Project or primary baseline".
Hope this helps.
Regards,
Arnold
Member for
17 years 8 monthsRE: Current Project finish date And Baseline finish are sa
first time i had perform the step.
Project Name Overrall
Maintain a Basleine as a Overall-B2
Then Baseline assign as Follows.
Project
Overall
PROJECT Basline
overall-B2
User baseline
PRIMARY
Overall-B2
The above step is also not worrking.
Thnaks
Member for
17 years 8 monthsRE: Current Project finish date And Baseline finish are sa
Project name is Overall
1.I have maintain a base Line as a Overall-2
2. Assign baseline as:
PROJECT
(overall)
PROJECT BASELINE
(current Project)
USER BASELINE
PRIMARY
(current-project)
hope find the solution.
Thanks
Member for
18 years 6 monthsRE: Current Project finish date And Baseline finish are sa
Hi Shahzad,
Are you sure you assign your baseline programme? Can you cite an example to make it easier to understand.
Regards.