Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Current Project finish date And Baseline finish are sa

10 replies [Last post]
Shahzad Ahmad
User offline. Last seen 15 years 17 weeks ago. Offline
Joined: 14 Feb 2008
Posts: 96

Hi---All

Could any one advise me .

I have update schedule in P6 after rescheduling the Current Project Finished date & Baseline finished date are same.

the fact is that we are late according to baseline sch.

my problem is Current Project Finished date not changing.

Thanks in advance for your help / advise.

Replies

Mark M
User offline. Last seen 13 years 46 weeks ago. Offline
Joined: 1 Jun 2008
Posts: 33
Groups: None
Gents

Please look at the following thread;
http://www.planningplanet.com/forum/forum_post.asp?fid=1&Cat=9&Top=48465

Particularly & I quote from David’s post;
"Also, a point to anyone who wishes to supply printed material (all be it scanned), what is the copyright of the document?

On this forum we have fantastically intelligent people who make a living from publishing great books and guides that we all use, by scanning and copying we are depriving that author of their rightful payment.

So, if you are not the author or rightful owner of the works or you do not have the specific permission of that entity to copy their works, please do not do it.

We will not condone copyright theft."

Regards
Mark
Shahzad Ahmad
User offline. Last seen 15 years 17 weeks ago. Offline
Joined: 14 Feb 2008
Posts: 96
Hi-All

Training Manual Is a Hrad Binder Books.

I will try to scan it then i can send to all of You.


Thanks
shahzad

Abeer Mahmoud
User offline. Last seen 8 years 23 weeks ago. Offline
Joined: 8 Jul 2008
Posts: 87
Hi Shahzad

can you please send to me the training manual my e-mail abeer3mt@hotmail.com

Thanks for your help.
Abeer
PINAN T.
User offline. Last seen 6 years 23 weeks ago. Offline
Joined: 20 Jul 2007
Posts: 102
hi shahzad

can you share to me the training manual

pinantoot@gmail.com

thank you
Shahzad Ahmad
User offline. Last seen 15 years 17 weeks ago. Offline
Joined: 14 Feb 2008
Posts: 96

Thanks , Mr Puy.

My explanation was not clear ..it was my main problem.

again Thanks.

I would like share my Training Manual which is full of example solving prob..etc..


Thanks so much for Your advice.

Regards
Shahzad
Shahzad Ahmad
User offline. Last seen 15 years 17 weeks ago. Offline
Joined: 14 Feb 2008
Posts: 96

Hi Mr. Puy

i create a copy of my master Schedule before update that

Basline -B1 which listed in my based Maintain base line Tab.

Ans. of your question yes i know how to save a copy thru Maintain basline / restored etc.

my problem has been solved with my training Manual.

In the manual
Arnold Puy
User offline. Last seen 9 years 42 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Shahzad,

If I understood you, your project & primary baseline is your current schedule. Therefore, your current & baseline schedule are the same.

Your current programme should came from the baseline programme and being updated weekly or monthly depending on your contract requirements.

My question is, do you know how to maintain & assign baseline? If not, then here are the steps:

1. Create a copy of your Approved Baseline Programme.
2. After creating, go to Project Menu --> Maintain Baseline then select "ADD".
3. Tick the "Convert another project to a new baseline of the current project" then OK.
4. Select the newly created copy of your Approved Baseline and assign & close.
5. Go to Project Menu --> Assign Baselines, and assign the added Approved Baseline to "Project or primary baseline".

Hope this helps.

Regards,

Arnold
Shahzad Ahmad
User offline. Last seen 15 years 17 weeks ago. Offline
Joined: 14 Feb 2008
Posts: 96
first time i had perform the step.

Project Name Overrall


Maintain a Basleine as a Overall-B2

Then Baseline assign as Follows.

Project

Overall

PROJECT Basline

overall-B2

User baseline
PRIMARY

Overall-B2

The above step is also not worrking.

Thnaks
Shahzad Ahmad
User offline. Last seen 15 years 17 weeks ago. Offline
Joined: 14 Feb 2008
Posts: 96
Project name is Overall

1.I have maintain a base Line as a Overall-2

2. Assign baseline as:

PROJECT
(overall)

PROJECT BASELINE
(current Project)

USER BASELINE
PRIMARY
(current-project)

hope find the solution.

Thanks

Arnold Puy
User offline. Last seen 9 years 42 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Shahzad,

Are you sure you assign your baseline programme? Can you cite an example to make it easier to understand.

Regards.