Current Project set as baseline shows different dates

2 replies [Last post]
Eckart Schenck
User offline. Last seen 4 years 21 weeks ago. Offline
Joined: 25 May 2005
Posts: 28
Groups: None

Hi,

 

in P6 I set the current project as primary and project baseline. In the bar chart view some start and finish dates are different. Anybody can help?

 

cheers

Replies

mukunda y
User offline. Last seen 10 years 44 weeks ago. Offline
Joined: 12 Nov 2008
Posts: 97
Groups: None

As Ronald said Concept of Baseline Start & FInish, Start & finish dates are different.. I advise you to understand the conecpt of these dates

Ronald Winter
User offline. Last seen 3 years 18 weeks ago. Offline
Joined: 4 Jan 2003
Posts: 928
Groups: None

Eckart,

 

When used as a Baseline, the schedule will show Planned Dates, which is sometimes different from Start Dates.  Good Luck!