Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Current Project set as baseline shows different dates

2 replies [Last post]
Eckart Schenck
User offline. Last seen 4 years 40 weeks ago. Offline
Joined: 25 May 2005
Posts: 28
Groups: None

Hi,

 

in P6 I set the current project as primary and project baseline. In the bar chart view some start and finish dates are different. Anybody can help?

 

cheers

Replies

mukunda y
User offline. Last seen 11 years 10 weeks ago. Offline
Joined: 12 Nov 2008
Posts: 97
Groups: None

As Ronald said Concept of Baseline Start & FInish, Start & finish dates are different.. I advise you to understand the conecpt of these dates

Ronald Winter
User offline. Last seen 3 years 37 weeks ago. Offline
Joined: 4 Jan 2003
Posts: 928
Groups: None

Eckart,

 

When used as a Baseline, the schedule will show Planned Dates, which is sometimes different from Start Dates.  Good Luck!