Youre welcome.
Hi Arnold,
Thanks for your answer,it was exacly what I was looking for.
Cheers,
Mohsen
Hi Mohsen,
You can do this by changing first the prefix, suffix & increment in project detail --> default tab --> auto-numbering defaults and uncheck the "Increment Activity ID based on selected activity" if you dont need to copy the existing Activitiy ID.
Try this.
Arnold