Copy and paste activities in P5

M
Mohsen M 👤 Member for 18 years 3 months
M
Mohsen M 👤 Member for 18 years 3 months

Hi Arnold,



Thanks for your answer,it was exacly what I was looking for.



Cheers,

Mohsen

A
Arnold Puy 👤 Member for 19 years 2 months

Hi Mohsen,



You can do this by changing first the prefix, suffix & increment in project detail --> default tab --> auto-numbering defaults and uncheck the "Increment Activity ID based on selected activity" if you don’t need to copy the existing Activitiy ID.



Try this.



Arnold