relationship links

2 replies [Last post]
Brian Mitton
User offline. Last seen 10 years 32 weeks ago. Offline
Joined: 27 Feb 2008
Posts: 16
Groups: None
hello my fellow planners, I have just shifted from P3 to P6 and am finding it a bit strange but so far so good, but HELP PLEASE.
When I create a baseline from my current schedule, the relationship links are attached to the baseline and not to the current schedule. How can I get this right, please.

Thanks

Brian

Replies

Brian Mitton
User offline. Last seen 10 years 32 weeks ago. Offline
Joined: 27 Feb 2008
Posts: 16
Groups: None
Thanks Mark, owe you a pint.
Mark M
User offline. Last seen 13 years 28 weeks ago. Offline
Joined: 1 Jun 2008
Posts: 33
Groups: None
Hi Brian

I think you’ll find if you "move down" your baseline bar in the list of bars, your relationship lines should line up with the activities. The list of bars seems to be a hierarchy from top to bottom which effects how particular bars etc are displayed.

Hope that helps

Cheers
Mark