Planned Dates = Start and Finish Dates

1 reply [Last post]
Richard Hill
User offline. Last seen 16 years 21 weeks ago. Offline
Joined: 31 May 2006
Posts: 4
Global Change in P6 is not as easy as it used to be (i.e. in P3)

For the life of me I can’t seem to get the parameters to say - Planned Start = Start and Planned Finish = Finish. I mean, come on the logic is simple enough then why can’t I find any parameter to say just that!

Thanks

Replies

Richard Hill
User offline. Last seen 16 years 21 weeks ago. Offline
Joined: 31 May 2006
Posts: 4
Apologies no need for reply back.
I figured it out in the end! Wasn’t what I expected but I entererd
Start is Greater than or Equal to PS and
Finish is Less than or eEqual to PF
> Then Planned Start is Equal to Start and
Planned Finish is Equal to Finish.