Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Successor Start Date same as Predecessor Finish date

6 replies [Last post]
Bhajan Chandrasek...
User offline. Last seen 7 years 49 weeks ago. Offline
Joined: 4 Nov 2010
Posts: 9
Groups: None

I am creating a baseline with all FS relationships. The activities have been assigned with a 20hr/day, 6 day work week. I am noticing that all the activities have the start dates of their predecessors' finish dates. ie, the successor is starting on the same day the predecessor finishes. Anyone knows whats going on here?

Replies

Zoltan Palffy
User offline. Last seen 3 weeks 2 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

glad I could help

Bhajan Chandrasek...
User offline. Last seen 7 years 49 weeks ago. Offline
Joined: 4 Nov 2010
Posts: 9
Groups: None

Thanks Zoltan. That worked.

 

Zoltan Palffy
User offline. Last seen 3 weeks 2 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

It doe snot matter if you want to use times or not the program uses time regardless if you want to or not.

the problem is the TIME if you turn on your times you will see the issue.

also show your durations in decimals 

both of these items can be turned on by going to edit users preference 

the show time setting is in the Dates tab click 12 hour and show minutes

and the duration decimal setting is in the units tab under duration format make it 2 decimals 

in your situation a 1 day activity is starting on the 2nd half on the first day at maybe 12:00 noon. So 4 hours are worked on 2nd half of the 1st day. Then the remaining 4 hours are started on the begriming of the 2nd day say 8:00 am.

This means the successor can start on the same day as the predecessor finished which would start on the second half of the day.

to fix this 

Make sure that all your remaining durations are in whole numbers  

when you schedule F9 your project make sure that the data date TIME is set to 8:00 am or the earliest hours that is being used by your calendars.

going forward for all actual start dates make sure that the TIME is 8:00 am or the earliest hours that is being used by your calendars.

make sure that any actual finish dates have the TIME of 5:00 pm or the latest hour begin used by your calendars. 

make sure all start constraints that the TIME is 8:00 am or the earliest hours that is being used by your calendars.

make sure all finish constraints that the TIME is set to 5:00 pm or the latest hour being used in your calendars. 

Bhajan Chandrasek...
User offline. Last seen 7 years 49 weeks ago. Offline
Joined: 4 Nov 2010
Posts: 9
Groups: None

"Check the project start hour against your calendars."

Thanks Rafael, Barrie. My User Preferences is selected for "Do not Use Time" because I dont want to display time in my Dates columns.

But to try out your suggestion, I selected "24 Hour" and changed the start date/time from 20 Jan 2016 02 to 20 Jan 2016 00. This caused my ODs to change !! and the original problem (Finish Date of Activity A=Start Date of Activity B) remains.

Barrie Callender
User offline. Last seen 1 year 28 weeks ago. Offline
Joined: 15 Feb 2006
Posts: 39
Groups: None

Rafael gives good advice and the first thing to do when implementing it is to go to Edit > User Preferences... and set P6 to show the Time on the Dates tab.  I prefer 24 Hour format, just make sure it is not on Do not show time.

Then you can look at the Data Date on the Project and verify it has a sensible time.  The Time should be before the starting time of your Calendar, but to be safe it is best to set it to 00:00.

You will need to Schedule your project if you had to change it.  Now you can see the Time element in the dates as well.

I hope that helps.

Barrie

Rafael Davila
User offline. Last seen 1 week 5 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241

Check the project start hour against your calendars.