Remain Finish Date vs Remain Start Date.

Hi everyone,

I am using Primavera PM6 to manage the coming workload of our team.

We have about 95 projects in progress with 4 to 9 activities in each project.

My problem occurs when I open many projects at the same time, the remaining units of some tasks are offset later in timescale and when I try to change the finish date, I get this message :

"Remain Finish Date cannot be earlier than Remain Start Date."

If anybody experienced the same problem, I would appreciate your help.

Thank you

Jean D

R
Ravi Katare 👤 Member for 12 years

Hi

Insert two columns

1. Early Remaining Start & 2. Early Remaining Finish.

For any Inprogress activity, ensure that Early Remaining Start < Early Remaining Finish. If not do it manually by selecting the customize date.

PS: dont forget to move data date after applying the actuals, its cause such kinda problem.

 

- Ravi

M
M Carey 👤 Member for 12 years 5 months

I also get this error when I have only one project open. In addition, I get another error that referes to the Remaining Start and Remaining Finish: Remaining Start cannot be Null; Remaining Finish cannot be Null.

Featured Partner

Top Posters

Kristian Mcwilliams
1 posts
dagogo dan - jumbo
2 posts
Alex Lyaschenko
27 posts
James Williams
75 posts
xerxes
0 posts
edwin
0 posts
jhalluk69
0 posts
wilmoahyi
0 posts
Peter Holroyd
51 posts
Robert Guers
1 posts

Our Partners