Remain Finish Date vs Remain Start Date.

Member for

11 years 4 months

Hi

Insert two columns

1. Early Remaining Start & 2. Early Remaining Finish.

For any Inprogress activity, ensure that Early Remaining Start < Early Remaining Finish. If not do it manually by selecting the customize date.

PS: dont forget to move data date after applying the actuals, its cause such kinda problem.

 

- Ravi

Member for

11 years 9 months

I also get this error when I have only one project open. In addition, I get another error that referes to the Remaining Start and Remaining Finish: Remaining Start cannot be Null; Remaining Finish cannot be Null.