Kevin Matthews
User offline. Last seen 15 years 24 weeks ago. Offline
Joined: 21 Jun 2006
Posts: 57
G’day,

We are finding that after exporting projects in P5 activity codes do not come across. These are Enterprise codes. Is it worth chaning the codes to global and/or project before exporting ?

Keep Planning..

Kevin.

Replies

Dieter Wambach
User offline. Last seen 8 years 10 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Hi Kevin
I had the same problem in P6. First I created the EPS-Activity Code. Then during the export the code’s values were created automatically and the activities remained properly assigned. This should work in P5 as well. (Thanks to the German hotline!)

Hope this works