You could do something very clever and write code to be called by Microsoft Project that can move data from P3e to Project. Ive used a combination of the P3e Import routines and VBA before to load data into P3e (including Activity Codes) and the same ideas will work the other way
Activity codes are no problem except...P3e, when it exports to MSP, will only send over the first ten sets of codes - responibility, discipline, type, area etc - so it may be an idea to sort them in the order in which you need them rather than alpha-numerically.
I use a couple of temporary codes - for those "odd" filters etc - which I make sure are at the bottom of the list at positions 11 and 12 onwards.
When in MSP, you can use the group and sort to sort the programme by the act codes rather than by the summary bars MSP creates. This means that you can effectively re-create the P3e look.
Dont forget that the MSP when re-imported MUST be properly progressed or everything will start at the data date! REAL pain in the whatsits! You will have to go into each activity and set the start and finish dates, percentage complete etc in MSP before exporting and re-importing - even via Excel. Something that most MSP users do not do.
(Found this out to my cost!)
Oh and dont forgt that the activity ids will change due to the way MSP works if you add in more activities in P3e.
Hope this helps. Post again if you need more as there are loads of users out there who must have other tips.
From this do I take it I am better to avoid activity codes altogether and use UDF’s instead, or will I find I need to use the activity codes to get some functionality?
Create a user defined field and use global change to copy the activity id into the user defined field - my system is down or else I would give you exact details.
When you then open MSP they will appear in the same field.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Barry,
sounds great in theory, unfortunately what I know about VBA could be written on the back of a stamp.
Paul
You could do something very clever and write code to be called by Microsoft Project that can move data from P3e to Project. Ive used a combination of the P3e Import routines and VBA before to load data into P3e (including Activity Codes) and the same ideas will work the other way
Nige,
I get confused with all the different versions of P3e, Im on V5 and have exported a test file into MSP but cannot find any of the activity codes.
Do I understand from your last message they should be there?
Paul
Paul
Activity codes are no problem except...P3e, when it exports to MSP, will only send over the first ten sets of codes - responibility, discipline, type, area etc - so it may be an idea to sort them in the order in which you need them rather than alpha-numerically.
I use a couple of temporary codes - for those "odd" filters etc - which I make sure are at the bottom of the list at positions 11 and 12 onwards.
When in MSP, you can use the group and sort to sort the programme by the act codes rather than by the summary bars MSP creates. This means that you can effectively re-create the P3e look.
Dont forget that the MSP when re-imported MUST be properly progressed or everything will start at the data date! REAL pain in the whatsits! You will have to go into each activity and set the start and finish dates, percentage complete etc in MSP before exporting and re-importing - even via Excel. Something that most MSP users do not do.
(Found this out to my cost!)
Oh and dont forgt that the activity ids will change due to the way MSP works if you add in more activities in P3e.
Hope this helps. Post again if you need more as there are loads of users out there who must have other tips.
Cheers
Nige
Thanks Nige,
From this do I take it I am better to avoid activity codes altogether and use UDF’s instead, or will I find I need to use the activity codes to get some functionality?
Paul
Create a user defined field and use global change to copy the activity id into the user defined field - my system is down or else I would give you exact details.
When you then open MSP they will appear in the same field.
Hope this helps
Nige