Hi All,
We have a 8500 plus activity network. We work on a remote server environment. THe schedule is based on WBS, but the grouping and sorting is done by activity codes. Multiple calendars are in use. Baseline has different data date (we have moved it since saving the baseline). Were using P3e.
We assigned a baseline recently, but when displaying the bars, the visual duration of the bar in the gantt chart section does not represnt the dates we see on the Bl1 start and Bl1 finsih columns. This has us all puzzled, we cant report our baseline, because it shows incorrectly.
Additionally in some cases, when you refresh (F5) the network, the baseline gets paired up with the current for only a few seconds until you click on the activity and the bar and dates return to its original date, this is not to bad, but if you dont click on the activity it remains with the incorrect information, so, in reality unless you know what exact date to expect, you cant know if the information is correct.
Has anyone experience this before or can anyone help me understand this strange behavior of P5e.
thanks.
Replies