Joined: 21 May 2007
Posts: 19
Groups: None
I am brand new to P5 and I am stumbling while importing from Excel files. I have these questions.

1) Should WBS codes be manually created (and referenced in the Excel Files)in P5 before exporting activities?

2) For some reason, my START dates are not importing correctly. They are defaulting to the DATA date. I have a DURATION column and FINISH colum and they are populating correctly, however all my START dates are defaulting to data dates.

I would really appreciate if anybody can shed some light on these issues.

Many thanks.

Replies

David Moses
User offline. Last seen 11 years 46 weeks ago. Offline
Joined: 20 Oct 2004
Posts: 122
That is great !!!

Keep on planning.....

Regards
Maya C
User offline. Last seen 15 years 42 weeks ago. Offline
Joined: 21 May 2007
Posts: 19
Groups: None
That really helps. This forum is great!

Thanks for your time, David and Oliver!
Oliver Melling
User offline. Last seen 5 years 5 days ago. Offline
Joined: 24 Apr 2007
Posts: 595
Groups: The GrapeVine
I agree with David,

you must have relationships between your activities in order to schedule the work. Otherwise all activities will move to the data date as there is nothing telling them they can’t start immediately.
David Moses
User offline. Last seen 11 years 46 weeks ago. Offline
Joined: 20 Oct 2004
Posts: 122
Hi There,

You are importing activities.Ok.

But if there is no relationship b/w activities, whether you import it or not, it is logical to see the start dates as data dates on the program.

Start dates, durations and finish dates are not enough to create a cpm. Relationship of those activites has to be defined as well.

Hope this helps
Maya C
User offline. Last seen 15 years 42 weeks ago. Offline
Joined: 21 May 2007
Posts: 19
Groups: None
I am not importing relationships, just activities.

Can you create WBS by importing?

David Moses
User offline. Last seen 11 years 46 weeks ago. Offline
Joined: 20 Oct 2004
Posts: 122
Hi There,

Did you check the relationship of activities?

I mean, while importing or exporting are you also importing or exporting predecessors or successors of activities.

It may cause such problem.

Regards,