Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

How to filter out only those activities driving a task?

4 replies [Last post]
David Podmore
User offline. Last seen 12 years 46 weeks ago. Offline
Joined: 26 Apr 2006
Posts: 74
Groups: None
I’ve just been asked if I can select a task towards the tail of a project (not neccessarily on THE critical path) and only display those tasks driving it. In effect a selective "critical path" in its own right if you see what I mean. Sounds like a good idea for a TOOLS button but there you go...

Replies

Arthur Godbeer
User offline. Last seen 15 years 19 weeks ago. Offline
Joined: 24 Jul 2006
Posts: 127
Groups: None
There is another existing enhancement request to show which relationships are driving, as a column.
Arthur Godbeer
User offline. Last seen 15 years 19 weeks ago. Offline
Joined: 24 Jul 2006
Posts: 127
Groups: None
I know this is not what you’re asking, but in case you don’t know, you can show (with a tick) which activities are driving, within the Predecessors or Relationships/Predecessors tabs.

To show driving relationships only in a layout is an existing enhancement request, according to the Primavera Knowledgebase.
David Podmore
User offline. Last seen 12 years 46 weeks ago. Offline
Joined: 26 Apr 2006
Posts: 74
Groups: None
Thanks for that Alex.

It’s not the simple answer I was hoping for! Ah well, I guess we will have to wait for Primavera to add it as a function.

Trace Logic is the closest we have found to an answer but it’s still not as good as "Display driving links only" in Pertmaster.

Again, thanks for your time.

David
Alex Wong
User offline. Last seen 11 years 35 weeks ago. Offline
Joined: 12 Feb 2003
Posts: 874
Groups: TILOS
David

to do that you need the un progress baseline schedule

What I normally do is since some of the activity is already completed and finish so it is very hard to filter and trace all the activity which is linked to this particular activity,
to filter that first step is use the baseline schedule (With the same logic sequence) (make a copy) - add a finish no later constraint in the tail activity with a very very early day 2 year before its early finish day or something like that
Schedule the plan
Filter the activity with excessive negative float,
Remove the constraint
Schedule the plan again

Then you will have all the activity that have assoication (link) with this activity
Sort the activity by total float
the lease float activities are the critical path for that particular activity, and the rest is on the critical path but not necessary as the critical activity

HTH

ALex