Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

How to display resource usage profile for filtered activities only

2 replies [Last post]
Asish Jayakumar
User offline. Last seen 11 years 33 weeks ago. Offline
Joined: 5 May 2013
Posts: 5
Groups: None

Hi all,

I am facing a problem.

I have created a programme and filtered some activities using Activity codes.

I want the resource usage profile for the filtered activities alone.

How can this be done?

-AJ

Replies

Arnold Puy
User offline. Last seen 10 years 9 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147

Hi Asish,

You can filter the group of activities using activity codes; however it is not possible to show or filter only the lists of the Resources assigned to those activities displayed while currently showing the “Resource Usage Profile” bottom layout.

I suggest you may use the functionality of “Tracking” which show only those resources assigned to each WBS level.

I hope the above assists you.

Cheers,

Arnold

Asish Jayakumar
User offline. Last seen 11 years 33 weeks ago. Offline
Joined: 5 May 2013
Posts: 5
Groups: None

I am using Primavera P6 R8.2.

-AJ