P3ec Expense actual not shown?

2 replies [Last post]
Jagathnarayanan A...
User offline. Last seen 11 years 1 week ago. Offline
Joined: 14 Jun 2006
Posts: 17
Groups: None
Hi, good day,

Anyone can tell me why the expenses is not having actual done even when I have the "Auto Compute Actuals" checked before my update of progress?.

Angyan

Replies

Alex Wong
User offline. Last seen 11 years 16 weeks ago. Offline
Joined: 12 Feb 2003
Posts: 874
Groups: TILOS
Hi

Expenses is use as a non-activity driven items in P3e. What you can do is if you want the actual is driven by the activity progress then you need to use resource.

HTH

Alex
David Kelly
User offline. Last seen 1 year 50 weeks ago. Offline
Joined: 19 Oct 2004
Posts: 630
This is a well known "feature" and not much loved. Auto-compute actual expenses are driven by the planned start and finish dates, NOT the actual start/ actual finish.