Hi,
In an already existing program, I tried to give a finish date for an activity.
However, it takes start date as finish date.
Upon completely moving out the start date & finish date & then trying to re-enter both of them, it accepts and shows activity %=100
HOwever,in the resources, there seem to be remaining units still left out instead of zero.
Kindly advise.
Thanks
at the activity level in the resource tab right click an choose Customize Resource Column and expand the General category
on the left hand side check auto compute actuals and bring it to the right hand side
make sure that this box is checked.