Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Actuals given,activiy %=100 but there are few remaining units in resources shown

1 reply [Last post]
karthikeyan V
User offline. Last seen 9 years 13 weeks ago. Offline
Joined: 22 Aug 2015
Posts: 2
Groups: None

Hi,

In an already existing program, I tried to give a finish date for an activity.

However, it takes start date as finish date.

Upon completely moving out the start date & finish date & then trying to re-enter both of them, it accepts and shows activity %=100

HOwever,in the resources, there seem to be remaining units still left out instead of zero.

Kindly advise.

Thanks

Replies

Zoltan Palffy
User offline. Last seen 3 weeks 6 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

at the activity level in the resource tab right click an choose Customize Resource Column and expand the General category

on the left hand side check auto compute actuals and bring it to the right hand side 

make sure that this box is checked.