Actuals given,activiy %=100 but there are few remaining units in resources shown

Hi,

In an already existing program, I tried to give a finish date for an activity.

However, it takes start date as finish date.

Upon completely moving out the start date & finish date & then trying to re-enter both of them, it accepts and shows activity %=100

HOwever,in the resources, there seem to be remaining units still left out instead of zero.

Kindly advise.

Thanks

Z
Zoltan Palffy 👤 Member for 16 years 10 months

at the activity level in the resource tab right click an choose Customize Resource Column and expand the General category

on the left hand side check auto compute actuals and bring it to the right hand side 

make sure that this box is checked. 

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts