Actuals given,activiy %=100 but there are few remaining units in resources shown

1 reply [Last post]
karthikeyan V
User offline. Last seen 8 years 46 weeks ago. Offline
Joined: 22 Aug 2015
Posts: 2
Groups: None

Hi,

In an already existing program, I tried to give a finish date for an activity.

However, it takes start date as finish date.

Upon completely moving out the start date & finish date & then trying to re-enter both of them, it accepts and shows activity %=100

HOwever,in the resources, there seem to be remaining units still left out instead of zero.

Kindly advise.

Thanks

Replies

Zoltan Palffy
User offline. Last seen 16 weeks 2 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

at the activity level in the resource tab right click an choose Customize Resource Column and expand the General category

on the left hand side check auto compute actuals and bring it to the right hand side 

make sure that this box is checked.