Performance % complete to be shown as BL1 Column

5 replies [Last post]
Haresh Jayanth
User offline. Last seen 6 years 21 weeks ago. Offline
Joined: 24 Aug 2006
Posts: 219

Dear All,

Why dont we have a column to choose Baseline perrformance % complete in P6. How can we get a column to show this ?? Any ideas from any expert.

regards,

 

Haresh Jayanth

Replies

Jerome Soriano
User offline. Last seen 9 years 50 weeks ago. Offline
Joined: 28 Oct 2010
Posts: 16

@ haresh,

planned performance % complete @ any given date (data date) is the schedule % complete.

so what you are looking for is exactly the "schedule % complete".

you can check in your schedule that schedule % complete = planned value cost/baseline budgeted cost

Jerome Soriano
User offline. Last seen 9 years 50 weeks ago. Offline
Joined: 28 Oct 2010
Posts: 16

@ haresh,

planned performance % complete @ any given date (data date) is the schedule % complete.

so what you are looking for is exactly the "schedule % complete".

you can check in your schedule that schedule % complete = planned value cost/baseline budgeted cost

PINAN T.
User offline. Last seen 6 years 4 weeks ago. Offline
Joined: 20 Jul 2007
Posts: 102

hi

what do you have in performance % that is not available in schedule %?

they are the same

Haresh Jayanth
User offline. Last seen 6 years 21 weeks ago. Offline
Joined: 24 Aug 2006
Posts: 219

Dear Jerome,

I want BL1 performance% complete column in the updated program. But P6.7 , doesnt have any provision of having a column as BL1 Performance % complete. The same column can be seen in Updated program i.e. performance % complete. How to get this column , where i can show the planned performance % complete as any given date.

regards,

 

Haresh Jayanth

Jerome Soriano
User offline. Last seen 9 years 50 weeks ago. Offline
Joined: 28 Oct 2010
Posts: 16

i think you want to see the schedule % complete.

schedule % complete = planned value cost/budgeted cost