Duration calculation by calendar

5 replies [Last post]
Dave Dodds
User offline. Last seen 5 years 5 weeks ago. Offline
Joined: 26 Jul 2006
Posts: 18
Groups: None
Does anyone know how to change the duration calculation when you change calendar after the project has been set up.

eg.
I have a plan that was set up using a 1-8-5 calendar, I have changed the activities to a 2-10-7 calendar, but the duration still shows using a 1-8-5 calendar.

Cheers
Dave

Replies

MK TSE
User offline. Last seen 4 years 25 weeks ago. Offline
Joined: 27 Feb 2002
Posts: 550
Groups: None
sorry to let us know, no change in P6. the "duration" is determined by user perference within the "calculated dates" by defined calendar.

Which means the display value in duration is keep on changing if user preference is changed.
David Kelly
User offline. Last seen 2 years 17 weeks ago. Offline
Joined: 19 Oct 2004
Posts: 630
Version 5 is the same. No "rumors" that version 6 will be any different BUT will probably allow a work-around.
Dave Dodds
User offline. Last seen 5 years 5 weeks ago. Offline
Joined: 26 Jul 2006
Posts: 18
Groups: None
Dave,
Thanks, I just discussed this with our admin. It does pose a problem to our field plans that do not work 1-8-5. The default for our database has to be 1-8-5 for mfg. Do you know if version 5 has address this?
BTW, 3-1 would have been easy with Utd. It is going to be a tough season as an arab.

Alex,
1-8-5 is 1 shift, 8 hours, 5 days. Therefore 2-10-7 is 2 shifts, 10 hours, 7 days. I don’t know if this is just Canadian terminology, but it makes sense to me.

Cheers and Thanks for the help.

Dave
David Kelly
User offline. Last seen 2 years 17 weeks ago. Offline
Joined: 19 Oct 2004
Posts: 630
Let me guess.

You changed all the activity’s calandars, but mysteriously all the durations for the summary bars have stayed the same?

In P3e all summary durations are calculated as the number of working periods between the start and finish of the summary bar as measured on the database’s default calandar. The default calandar is "ticked in the global calandar display.
Alex Wong
User offline. Last seen 11 years 35 weeks ago. Offline
Joined: 12 Feb 2003
Posts: 874
Groups: TILOS
Dave

1 8 5 ??

1:oo - 8:00 5 days??
or
1 Days 8:00 - 5:00
or
1 shift, 8 hrs days and 5 days??

Please clarify

Alex