P3 e/c Baseline

2 replies [Last post]
Karim Mounir
User offline. Last seen 10 years 7 weeks ago. Offline
Joined: 5 Apr 2006
Posts: 314
Groups: None
Hi,

If i didn’t make a baseline in a schedule (eg. didn’t convert another schedule to be the baseline nor made a copy of the current schedule to be the baseline ), then P3 e/c assigns the current schedule to be the baseline, OK.

Then the target activities dates should be the same as of the updated dates of the ongoing activities, right ?

This isn’t right for the ongoing activities or completed activities, only works with te activities which didn’t start till the data date, CLAIRFY please!!

Replies

Karim Mounir
User offline. Last seen 10 years 7 weeks ago. Offline
Joined: 5 Apr 2006
Posts: 314
Groups: None
thanx
Steven Oliver
User offline. Last seen 11 years 45 weeks ago. Offline
Joined: 8 Nov 2002
Posts: 313
Groups: None
P3e uses the fields Planned Start and planned Finish as the basis of the baseline. This works fine for activities with no progress, but not so good for completed and especially in-progress activities.

Use Global Change to set Planned Start/planned Finish equal to Start/Finish.