Exporting from P3 e/c to P3

3 replies [Last post]
Mirza Imam Baig
User offline. Last seen 6 years 18 weeks ago. Offline
Joined: 29 Apr 2003
Posts: 39
Groups: None
Hi Planners,
Greetings

I prepared the Baseline Design Schedule in used P3 e/c. I am listing down few of the Activities of the Schedule below. My planning Unit is “Day”. and the Calendar is 5 day Calendar with Sat, Sun, Mon, Tue and Wed as Working days and Thursday and Friday as Non-working days.

In P3e/c

S. No. Activity Description Orig. Duration Early Start Early Finish

1 Mechanical Design 114 d 26-Dec-05 08-Jun-06
2 Electrical Design 106 d 05-Jan-06 08-Jun-06
3 Structural Design 81 d 13-Feb-06 08-Jun-06


Later the Client asked us to generate the same schedule in P3. So I exported the schedule from P3 e/c to P3. After exporting, I experienced lot of inconvenience due to the changes in dates and durations. I am listing down the same activities in P3 (after exporting)

In P3

S. No. Activity Description Orig. Duration Early Start Early Finish

1 Mechanical Design 143 26DEC05 12JUL062
2 Electrical Design 133 09JAN06 12JUL06
3 Structural Design 101 22FEB06 12JUL06

I could not understand why this happened. When I checked the calendar in P3, it shows the same working days and non-working days as that of P3e/c.

Can anyone help me on this….. Why this happened and how to overcome this kind of problem in future.

Thanks.

Replies

Mirza Imam Baig
User offline. Last seen 6 years 18 weeks ago. Offline
Joined: 29 Apr 2003
Posts: 39
Groups: None
Hi friends,

Thanks for the response
Alan Callow
User offline. Last seen 19 years 22 weeks ago. Offline
Joined: 14 Jan 2005
Posts: 8
Under Admin > Admin Preferences > Time periods > check the default time this may affect duration unless shown in hours
Henk van der Heide
User offline. Last seen 6 years 41 weeks ago. Offline
Joined: 7 Aug 2004
Posts: 101
Imam,

I think you’ve a calender problem
Best way to find out: Check both durations in Hours.
It seems that 1 day is not always 8 hours work. (this can be the problem).

Regards

Henk