Hi Planners,
Greetings
I prepared the Baseline Design Schedule in used P3 e/c. I am listing down few of the Activities of the Schedule below. My planning Unit is “Day”. and the Calendar is 5 day Calendar with Sat, Sun, Mon, Tue and Wed as Working days and Thursday and Friday as Non-working days.
In P3e/c
S. No. Activity Description Orig. Duration Early Start Early Finish
1 Mechanical Design 114 d 26-Dec-05 08-Jun-06
2 Electrical Design 106 d 05-Jan-06 08-Jun-06
3 Structural Design 81 d 13-Feb-06 08-Jun-06
Later the Client asked us to generate the same schedule in P3. So I exported the schedule from P3 e/c to P3. After exporting, I experienced lot of inconvenience due to the changes in dates and durations. I am listing down the same activities in P3 (after exporting)
In P3
S. No. Activity Description Orig. Duration Early Start Early Finish
1 Mechanical Design 143 26DEC05 12JUL062
2 Electrical Design 133 09JAN06 12JUL06
3 Structural Design 101 22FEB06 12JUL06
I could not understand why this happened. When I checked the calendar in P3, it shows the same working days and non-working days as that of P3e/c.
Can anyone help me on this….. Why this happened and how to overcome this kind of problem in future.
Thanks.