WBS calendar

9 replies [Last post]
Marcio Sampaio
User offline. Last seen 11 years 50 weeks ago. Offline
Joined: 7 Nov 2005
Posts: 658
Dear all,

Why do sometimes a wbs level duration is diferent than its total activities duration??

I have a small shcedulle, only onde calendar (for project and activities) and this conflit is happening.

Which calendar wbs cosider?? Is it "time periods" defined in Admin Preferences??

Regards.

Replies

Marcio Sampaio
User offline. Last seen 11 years 50 weeks ago. Offline
Joined: 7 Nov 2005
Posts: 658
Ok Kevin ... i’m sending it.

Thanks and regards.
Kevin Button
User offline. Last seen 2 years 34 weeks ago. Offline
Joined: 16 Jul 2003
Posts: 112
Groups: None
I think it’s a good idea, send email to primavera with this enhancement request and they will put it on the list.

Cheers
Marcio Sampaio
User offline. Last seen 11 years 50 weeks ago. Offline
Joined: 7 Nov 2005
Posts: 658
Do u think it is possible for next release??
Marcio Sampaio
User offline. Last seen 11 years 50 weeks ago. Offline
Joined: 7 Nov 2005
Posts: 658
I understand and i’m agree.

But I think that the ideal should be P5 to allows user to choose which calendar wbs consider.

Regards.
Marcio Sampaio
User offline. Last seen 11 years 50 weeks ago. Offline
Joined: 7 Nov 2005
Posts: 658
I understand and i’m agree.

But I think that the ideal should be P5 to allows user to choose which calendar wbs consider.

Regards.
Niek Zonneveld
User offline. Last seen 2 years 19 weeks ago. Offline
Joined: 17 Mar 2005
Posts: 188
Groups: None
Yep that’s the case.

I don’t see how it could work any other way, because how would you treat grouped activities with multiple calendars? (not just by WBS, but also any other (combined) grouping)

H.T.H.
Marcio Sampaio
User offline. Last seen 11 years 50 weeks ago. Offline
Joined: 7 Nov 2005
Posts: 658
Niek,

I’m working with P3e ... is it still happening in P5??

Regards.
Marcio Sampaio
User offline. Last seen 11 years 50 weeks ago. Offline
Joined: 7 Nov 2005
Posts: 658
Thanks a lot Niek.
Niek Zonneveld
User offline. Last seen 2 years 19 weeks ago. Offline
Joined: 17 Mar 2005
Posts: 188
Groups: None
PRIM2849:

The original duration in the WBS summary bands is calculated as the following:

Latest Planned Finish - The Earliest Planned Start.

Project Manager uses the default Global calendar to determine the number of timeperiods based on the above calculation.

********************

This means that if your project calendar and the default global calendar are not the same, you can have deviations.

Hope this helps,

Niek.