Copy & Paste between programmes

7 replies [Last post]
Andrew Edwards
User offline. Last seen 7 years 6 weeks ago. Offline
Joined: 9 Nov 2004
Posts: 15
Groups: None
Can anybody shed some light on the best way to do this? I know this is a stupidly simple question, but right now my colleague and I are at the end of our tether with it. We’ve tried almost every method we can think of, but still P3e stubbornly refuses to paste the copied activities into the destination programme.

Any help would be greatly appreciated.

Andy

Replies

Andrew Edwards
User offline. Last seen 7 years 6 weeks ago. Offline
Joined: 9 Nov 2004
Posts: 15
Groups: None
How very true. Given that I’m staff here, I really shouldn’t complain but.....
Steven Oliver
User offline. Last seen 12 years 1 week ago. Offline
Joined: 8 Nov 2002
Posts: 313
Groups: None
Guilty. But "work" and "NR" should never be used in the same sentence
Andrew Edwards
User offline. Last seen 7 years 6 weeks ago. Offline
Joined: 9 Nov 2004
Posts: 15
Groups: None
Cheers Steven,

Did you work at NR in York recently?
Steven Oliver
User offline. Last seen 12 years 1 week ago. Offline
Joined: 8 Nov 2002
Posts: 313
Groups: None
Incidentally, I’ve just copied activities in the activity view from one project to another without any trouble.

You do have permissions for both projects, dont you ?
Steven Oliver
User offline. Last seen 12 years 1 week ago. Offline
Joined: 8 Nov 2002
Posts: 313
Groups: None
No, it will copy all activities. Just delete those you dont want. Or in your source project segregate the activities you want into a temp wbs, copy to your target and then move source activities back to the original wbs.

Andrew Edwards
User offline. Last seen 7 years 6 weeks ago. Offline
Joined: 9 Nov 2004
Posts: 15
Groups: None
Thanks Steven, does this work with partial sets of activities from the WBS?

Andy
Steven Oliver
User offline. Last seen 12 years 1 week ago. Offline
Joined: 8 Nov 2002
Posts: 313
Groups: None
Open both Source and Target, select Project, Wbs and copy your source wbs to target.


HTH