Copy & Paste Resource Assignments?

2 replies [Last post]
beck lee
User offline. Last seen 16 years 28 weeks ago. Offline
Joined: 10 Dec 2006
Posts: 11
Groups: None
Hi Guys,

Since you are ever so helpful and fast to respond (not to mention extremely intelligent!), here is a quick question for you..

In P5, can I copy and paste resource assignements between activities?

Ta,

Beck

Replies

beck lee
User offline. Last seen 16 years 28 weeks ago. Offline
Joined: 10 Dec 2006
Posts: 11
Groups: None
Thanks Kevin..

I will just have to stick with the multiple assignment option and the replace facility.. Was just hoping it would copy resource units over as well..

Thanks again,

Beck
Kevin Button
User offline. Last seen 2 years 34 weeks ago. Offline
Joined: 16 Jul 2003
Posts: 112
Groups: None
Unfortunately you can’t copy assignments between activities. However you can do a multiple resource assignment to multiple activities in one go. Just select the activities, click the Assign Resources button on the Command Bar (right side of screen), select the resources and hit the assign button.

Cheers