I need your help...
facts,
1. I have 800 activities on my scheduled project that mainly consist of 24 buildings and roadworks.
2. When i scheduled the project, there are 46 milestone activities which have an invalid relationships.
3. All this activities were completion activities which are linked to project completion.
5. Please advice me on how to resolve this problem.
and my expected critical path was not the one appeared on the scheduled project. Advice please!!!!!!!11