Ive been playing around with P3ec after using P3.1 & Suretrak for the last year. P3ec does have some advantages, but Ive run into some problems with the program. Most have been minor, such as only being able to put 1 curtain in the schedule or not being able to Print preview.
However, today I ran into a problem. I had done a monthly update (for the owner) for last month, in which I had statused an activity projecting to be 100% complete. However, because of circumstances the activity has yet to start. So when I go back to the schedule and try to unstatus the activity, P3ec wont allow me to change the % complete. The only thing I can alter is the actual start and actual finish.
I talked to another scheduler and he said that Primavera 2.xx had a similar problem. Is there any way around this problem, besides deleting the activity and adding it back in?