P3 to P3ec 3.5.1 conversion - errors

3 replies [Last post]
Dhananjay Kulkarni
User offline. Last seen 21 years 10 weeks ago. Offline
Joined: 28 Feb 2003
Posts: 4
Groups: None
I tried to convert the project from P3 to P3ec. but to my disappointment, after rescheduling in p3ec it is showing me -ve total float. but the same schedule in p3 does not have any -ve float. i checked calendars, data date, duration types, advanced scheduling options(tried all different options, even lag calendars). everything seems ok. but still it shows -ve total float.

my project has must finish date, which i used in scheduling option too.

am i missing on something? please help.

Thank you in advance.

Replies

Forum Guest
User offline. Last seen 2 years 40 weeks ago. Offline
Joined: 28 Jan 2009
Posts: 1
Groups: None
We have the same problem, but caused by calendar, not sure why

Suresh Kumar
Dhananjay Kulkarni
User offline. Last seen 21 years 10 weeks ago. Offline
Joined: 28 Feb 2003
Posts: 4
Groups: None

Thanks Paul for your views and suggestion.

I found the differneces between p3 and p3ec like Original duration, remaining duration. so i changed those in p3ec. and somehow managed the -ve total float to -1 now.
I think, that remaining -1 total float is because of level of effort which was hammock in p3.

Anyway, thnaks a lot.

Dhananjay
Paul Harris
User offline. Last seen 1 year 16 weeks ago. Offline
Joined: 11 Apr 2001
Posts: 618
I am unable to specifically tell you why your project is giving negative float but here are some things to think about.

All scheduling products calculate differently and importing a schedule is a data conversion not a project conversion and when I end up with the same answer after converting anything but a simple project especially one with progress I would consider myself very lucky.

To find the problem you should look at the start and finish dates and floats of the activities one at a time from the start until you find difference. At this point you may wish to check the calendars, lags and lag calendar. Primavera Enterprise has an option of 4 lag calendars, not just the predecessor as in P3. Check the autocost rules maybe the Remaining Duration has calculated differently or you may find a constraint has been handled differently. I have noticed that P3e handles Expected Finish Constraints differently to P3 when an Activity has progress, but I have not work through the issues to find out why.

Regards
Paul E Harris
www.eh.com.au