Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Changing calender for group of activities, .....

1 reply [Last post]
X Planner
User offline. Last seen 8 years 42 weeks ago. Offline
Joined: 17 Jun 2002
Posts: 78
Groups: None
Good day guys,

....I wonder if it is possible to select a group of activities and then change the calender for them??,cos i failed doing this , i thought i might made anything wrong.

Also i noticed that codes never change in the organization menu when switchin between different projects.. any idea?

Again...while trying to print the resources usage profile, i only get the left panel which is the activity colums but
i didnot get the gantt or the profile (i checked the print options (and i think it was ok) ??

Thanx very much in advance .

Replies

Forum Guest
User offline. Last seen 18 weeks 2 days ago. Offline
Joined: 28 Jan 2009
Posts: 2
Groups: None
up...