Changing calender for group of activities, .....

1 reply [Last post]
X Planner
User offline. Last seen 8 years 23 weeks ago. Offline
Joined: 17 Jun 2002
Posts: 78
Groups: None
Good day guys,

....I wonder if it is possible to select a group of activities and then change the calender for them??,cos i failed doing this , i thought i might made anything wrong.

Also i noticed that codes never change in the organization menu when switchin between different projects.. any idea?

Again...while trying to print the resources usage profile, i only get the left panel which is the activity colums but
i didnot get the gantt or the profile (i checked the print options (and i think it was ok) ??

Thanx very much in advance .

Replies

Forum Guest
User offline. Last seen 2 years 40 weeks ago. Offline
Joined: 28 Jan 2009
Posts: 1
Groups: None
up...