Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Discontinuance of activities in P3e

6 replies [Last post]
Tamas Sipos
User offline. Last seen 5 years 34 weeks ago. Offline
Joined: 2 Mar 2004
Posts: 13
Dear Friends!

Is it possible to discontinue (and later to continue) activities in P3e?

Regards: Tamas

Replies

Niek Zonneveld
User offline. Last seen 2 years 19 weeks ago. Offline
Joined: 17 Mar 2005
Posts: 188
Groups: None
I don’t know what Tamas is exactly trying to achieve, but I’m not a big fan of suspend/resume either.

If you want to control when resources work on a certain activity, you can also use assignment lag and/or manually overrule the start and finish dates of each assignment.

Having said that, in general it’s a lot of work and the resource planning does not get more accurate.

Hope this helps,

Niek.
Ronald Winter
User offline. Last seen 3 years 23 weeks ago. Offline
Joined: 4 Jan 2003
Posts: 928
Groups: None
Don’t forget that Suspend/Resume is intended to chronicle the As-Built condition, not a planned suspense in the future. A planned suspense in the future does not make sense in CPM rules and has no definition of how it should work, or look for that matter. Good luck!
Julie Scully
User offline. Last seen 16 years 42 weeks ago. Offline
Joined: 9 Nov 2005
Posts: 25
I have used suspend and resume successfully. If it is in the gantt chart that it is not appearing, that’s because you need to format some new bars to display it. Refer to Primavera Knowledgebase bulletin #prim12322.
Craig Freake
User offline. Last seen 3 years 19 weeks ago. Offline
Joined: 7 Oct 2005
Posts: 17
Groups: None
In P3e, I need to split an activity but I am still in planning mode.....I ried the Suspend / Resume option but no success...Any heklp wopuld be greatly appreciated....
Alex Wong
User offline. Last seen 11 years 21 weeks ago. Offline
Joined: 12 Feb 2003
Posts: 874
Groups: TILOS
You can add a milestone on top of the activity that you would like to discontinuos and set a FS relationship between the Finish Milestone and your activity,

Force the FM to a predicted date that you think the activity will be resume.

That way you can control the resume date with visual.

Hope that help
Forum Guest
User offline. Last seen 4 weeks 2 hours ago. Offline
Joined: 28 Jan 2009
Posts: 2
Groups: None
If you mean similar to split activity in MSP parlance, the only way I can think of is by assigning a new calendar to the activity and making the ’stoppage period’ non-working