Milestone’s moving ahead of all activites

4 replies [Last post]
Mike Miller
User offline. Last seen 12 years 17 weeks ago. Offline
Joined: 6 May 2010
Posts: 20
Groups: None
Referencing the image, when I use milestones Primavera will automatically move them above all the tasks. For example the "End State Inspections" milestone will move above the other activities even when I have the activities set as a predecessor. Why is primavera doing this?

Replies

Shah. HB
User offline. Last seen 49 weeks 3 days ago. Offline
Joined: 25 Nov 2008
Posts: 773
Hi mike

keep exploring you might get many new stuff
Mike Miller
User offline. Last seen 12 years 17 weeks ago. Offline
Joined: 6 May 2010
Posts: 20
Groups: None
Thanks for the advice. I got one section to be organized correctly by manipulating the organize feature, now I have to go through the other sections and code them so that they are in the proper order as well.
Shah. HB
User offline. Last seen 49 weeks 3 days ago. Offline
Joined: 25 Nov 2008
Posts: 773
Hi Mike

In addition to Rodel’s advise , check in
format --> Organize and choose the bottom sort and group option as early dates ,it might solve your issues
Rodel Marasigan
User offline. Last seen 4 days 13 hours ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Mike,
It seems that your sorting is based on activity id and start date. Change the sort sequence or change the activity id base on your requirements.