Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

WBS Summary Activites Moving with Data Date

1 reply [Last post]
Nathan Siva
User offline. Last seen 41 weeks 6 days ago. Offline
Joined: 28 Apr 2014
Posts: 30
Groups: None

Hi Experts,

 

I'm Facing an issue, In my schedule, even though some of the WBS summary activities are already started, they are moving with the data date of the schedule.

Every time when I'm changing the data date, WBS summary activites moving forward with the data dates and then I have to revise back to previous dates of WBS Summary.

Kindly advise.

Replies

Zoltan Palffy
User offline. Last seen 1 week 15 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

it is doing what its is supposed to do.

It summarizes ALL activities under that WBS.

It will use the earliest actual start date of any activites under that wbs and the latest finish (not late finish date) date for the  activities under that wbs. 

so if you update the schedule and things move to the right then the wbs summary will move to the right.