Auto Link ???? (Multiple Activites to Same Successor)

4 replies [Last post]
Sami Abu al Heijaa
User offline. Last seen 13 years 51 weeks ago. Offline
Joined: 11 Sep 2006
Posts: 13
Groups: None
Hi All


Can any body tell me how to link multiple activites to the same successor , actulley I tried the Global Change but i could’nt make it


thanks

sami

Replies

Hemanth Kumar
User offline. Last seen 1 year 21 weeks ago. Offline
Joined: 1 Nov 2002
Posts: 260
Groups: None
I Persume You Want To Link A Group Of Activities To One Activity Or Milestone As Predecessers And You Dont Know Linking Data With Excel
Try This

First Link Manualy to One Predecessor
Open The Activity Form
Open Successor Form
Select The Linked Activity ( From Group Of Activities )
You Will See In the Form the ID of Successor
Now Copy That Actvity ID

Select another Activiity
Paste Acivity ID in The Succsessor Form
Click Another Activity
Go On


Ahmed Saudagar
User offline. Last seen 2 weeks 2 days ago. Offline
Joined: 30 Jan 2006
Posts: 10
Groups: GPC Qatar

Sami

As to import from Excel, you must create a DBF file with feilds of "ACT" as the first column where you list Activity IDs of all the activities to which you wish to add the common successor to. In the second column you must have "SUC" as the field data where you will fill the common completion Activity ID. In addition you must have Fields of "LAG" which must be ’0’ and ’REL’ which must be ’FS’ for all the activities.

Regards

Sami Abu al Heijaa
User offline. Last seen 13 years 51 weeks ago. Offline
Joined: 11 Sep 2006
Posts: 13
Groups: None
Dear Dayanidhi


My problrm that these activites are not linked at all to any successo so I made a completion activity which i want to link them to thats it !! have you got the picture
by the way it was a qustion too how can i export those info to excel



thnx

sami
Dayanidhi Dhandapany
User offline. Last seen 3 years 34 weeks ago. Offline
Joined: 18 Mar 2003
Posts: 470
Groups: None
I think you can export the activities with successor information, then try to do the changes in Excel and import back to P3