Total Manpower in Activity Column area

4 replies [Last post]
Anbin Ponnith
User offline. Last seen 8 years 36 weeks ago. Offline
Joined: 8 Jun 2009
Posts: 158
Dear All,

How can I show the total manpower for the activities in the column area.If I assign manpower in the resource and assign it to the activities and get displayed in the budgeted quantity the column displays the addition of all the resources assigned.

Please help me how can I get separate Manpower Summation.

With Thanks & Regards,

Anbin Ponnith.P

Replies

Samoray Mega
User offline. Last seen 13 years 6 days ago. Offline
Joined: 3 Nov 2009
Posts: 3
Thanks about your clarification but i think type of custom data item not precision but character

thanks alot
Shah. HB
User offline. Last seen 49 weeks 4 days ago. Offline
Joined: 25 Nov 2008
Posts: 773
Please check it up

select data from menu option and choose custom data items and under activity option type it as RESO ,type character and choose length of it and description same for BQ1 type precision
then goto global change set the condition to select the particular resource you required

If RES EQ LABOUR
Then RESO EQ RES

this would display resource name, you could select from column option under name RESO

thn set the following condition for BQ1 to display quantities

If RES EQ LABOUR
Then BQ1 EQ BQ


Anbin Ponnith
User offline. Last seen 8 years 36 weeks ago. Offline
Joined: 8 Jun 2009
Posts: 158
Thanks for the Reply Shahul,

Exactly the same .I need them in the Column area to be displayed.(only the manpower).Also not using tabular reporting option.


Regards,

Anbin
Shah. HB
User offline. Last seen 49 weeks 4 days ago. Offline
Joined: 25 Nov 2008
Posts: 773
hi
you need the resource name and quantity to be displayed against each activity ?