Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Total Float at Completed Activities

7 replies [Last post]
Mohamed Salah
User offline. Last seen 11 years 4 weeks ago. Offline
Joined: 18 May 2003
Posts: 8
Groups: None
Dear sirs It pleasure to me to contact you . if you please could some one answer me How P3 Calculate the total float for completed activities Pct = 100% ? That value diaper at TF Column but it Calculated& appear at Edit bar Regards M Salah ensalah1001@hotmail.com

Replies

MK TSE
User offline. Last seen 4 years 25 weeks ago. Offline
Joined: 27 Feb 2002
Posts: 550
Groups: None
The discussions may induce a concept that a completed activity still have total float?

If do, the value will change after scheduling and levelling. If no change in value, either software bug (forget to blank the field or invisable the value for a completed activity) or other reason.
Scott Herold
User offline. Last seen 20 years 48 weeks ago. Offline
Joined: 26 Nov 2003
Posts: 4
Groups: None
To carry Ron’s point one step further, Primavera’s decision to hide the total float on completed activities is one of the many reasons it is difficult to analyze float in a P3 schedule when there is out-of-seqence progress. Even though an activity is completed (out-of-seqence), it’s zero day remaining duration is still calculated according to the network logic (assuming retained logic is being used), with early & late dates , and total float being calculated.
Ronald Winter
User offline. Last seen 3 years 37 weeks ago. Offline
Joined: 4 Jan 2003
Posts: 928
Groups: None
It is a little known fact that all activities have a total float computation. Primavera just elects to not show it (with the exception of the fact mentioned below.) You cannot calculate a CPM schedule with out-of-sequence progress without including the completed activities in your computation. You ignore the fact that they are complete and just consider the remaining duration (zero.) Afterwards, Primavera forces the actual dates into the early and late fields (even they have forgotten why they do this) and blank out the total float display.
Jorge Taguinod
User offline. Last seen 2 years 49 weeks ago. Offline
Joined: 8 Jul 2003
Posts: 139
Since the Total Float is the amount of time you can delay an activity without delaying the project, then the TF for 100% completed activities is nil. You cannot delay an activity that has been completed already, can you?

Jorge
MK TSE
User offline. Last seen 4 years 25 weeks ago. Offline
Joined: 27 Feb 2002
Posts: 550
Groups: None
It seems it is the only location to view a hidden value, not to other screens and reports. I think it is a bug on P3.
The field keeps the latest TF value, it should be clear once completed.
Further, the value is grey is correct since TF is not editable.
MK TSE
User offline. Last seen 4 years 25 weeks ago. Offline
Joined: 27 Feb 2002
Posts: 550
Groups: None
If an activity is completed, the TF cell must be blank since TF to an completed activity is meaningless.
Steven Oliver
User offline. Last seen 12 years 1 week ago. Offline
Joined: 8 Nov 2002
Posts: 313
Groups: None
Irrespective of whatever planning tool you use, Total Float of a completed activity will always be = 0.