Percent weight in Primavera P3 S-curve

1 reply [Last post]
Chandan Kakati
User offline. Last seen 14 years 38 weeks ago. Offline
Joined: 19 May 2008
Posts: 8
Groups: None
Can anyone tell me how to assign percent weight for different phase of a project for producing a Project S-curve. I have a percent weight as Engineering:Procurement/Fab:Construction:Commissioning = 25%:15%:55%:5% which I need to assign to each phase S-curve and get a overall Project S-curve. e.g. suppose I have a % complete for engineering as 40%, the contribution it will make to overall progress as 40*25%=10%. Please help its really urgent.

Replies

mimoune djouallah
User offline. Last seen 5 years 5 weeks ago. Offline
Joined: 14 Oct 2006
Posts: 388
hi

you need to assign a resource, "call it manhour for simplification" to your program,
let’s say the total budget quantity for your program will be 100 Hours. thus :

Engineering = 25 hour
Procurement/Fab = 15 hour
Construction = 55 hour
Commissioning = 5 hour


HTH