Schedule with different Calendar ID

2 replies [Last post]
Jun Gallardo
User offline. Last seen 8 years 27 weeks ago. Offline
Joined: 12 Apr 2008
Posts: 22
Hello Planners,

I am working with a schedule with three calendar ID’s (6-days, 7-days and 5-days). In the summarization setting, P3 asks for calendar ID to use, what shall I use? Shall I use the the calendar ID which is assigned the most? (in this case, 6-day). Shall I be getting an accurate summary for the Percent Complete if P3 uses only one calendar id?

Please help. Regards.

Jun

Replies

Jun Gallardo
User offline. Last seen 8 years 27 weeks ago. Offline
Joined: 12 Apr 2008
Posts: 22
Mr. Iimos,

Thank you for your comment. So, using different calendar ID in a schedule (one schedule with 2 or more calendar ID’s assigned to several activities)should not be recommended?
Anoon Iimos
User offline. Last seen 2 years 30 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
I supposed you’ll be getting different results as well. A result for each calendar used.