Can’t edit Activity ID numbers?

2 replies [Last post]
David Ball
User offline. Last seen 5 years 14 weeks ago. Offline
Joined: 8 Aug 2007
Posts: 16
Hi all,

I have two schedules in P3. In one, I can click on an Activity ID then edit it to change the number.

In the other, the Activity IDs are greyed out when I select them and I am not able to edit them.

Any ideas on how I can set up the second schedule so that I can edit Activity IDs?

Thanks a lot.

Replies

Johny Kesserwany
User offline. Last seen 7 years 44 weeks ago. Offline
Joined: 18 Sep 2007
Posts: 118
In order to edit an Activity ID, the project must be open in exclusive mode.

To open a project exclusively,

1. Go to File, Open
2. Highlight the project
3. Mark the Exclusive checkbox
4. Click Open.

____________________________________________________

How to bypass Exclusive Access to edit Activity IDs:

Open the P3.INI file by going to Start, Run and type P3.INI.

In the Options section edit the following setting

[Options]
ExclForActIDEdit=0



Ferdinand U.
User offline. Last seen 7 years 12 weeks ago. Offline
Joined: 19 Jul 2007
Posts: 142
open the project as exclusive (check)

or edit the p3.ini

As per P3 help:

To edit activity IDs

Enter a zero (0) on the ExclForActIDEdit line in the [Options] section of the P3.INI file to allow editing of activity IDs without exclusive access:

ExclForActIDEdit=0

To require exclusive access to edit activity IDs, change this line to ExclForActIdEdit=1.