Log Record Problem

A
Anu Tor 👤 Member for 19 years 4 months
J
Johny Kesserwany 👤 Member for 18 years 9 months

Hi Anu,



This message appears in the Out-of-Sequence progress listing of a scheduling report when a successor activity starts too early to satisfy a finish-to-finish relationship with its predecessor. By default, P3 uses the contiguous duration scheduling option (Tools, Schedule, Options button), meaning that when a finish-to-finish predecessor delays its successor’s finish date, P3 also delays the successor’s start date because the workperiods of the activity must be contiguous. When the successor has an Actual Start date, P3 can not delay the start and the warning message is generated.



There are 2 options to prevent this message.



1. Remove the relationship between the two activities if it is no longer valid. This allows the remaining duration of the successor to be calculated from the Data date.



2. Go to Tools, Schedule and select the Options button. Schedule the project using the "Interruptible" durations option. If you choose Interruptible and a finish-to-finish predecessor delays an activity’s finish date, P3 delays only the finish of the activity; the start is scheduled separately on the Actual Start date.



Regards

Forum Sponsor

Top Posters

blake333_
0 posts
Mohammed Netarwala
12 posts
Moahmed
0 posts
S Z
4 posts
Iftikhar Awan P.Eng.
19 posts
ahmad rashidi
4 posts
paulciszewski
0 posts
Catalin Suditu
11 posts
Laraib Fatima
0 posts
Adrian Fletcher
12 posts