P3.1 Planned Percentage

3 replies [Last post]
Gavin Morris
User offline. Last seen 15 years 16 weeks ago. Offline
Joined: 11 Jan 2005
Posts: 6
Hi, I just returned to P3.1 (from p6) and am struggling with getting the Planned Percent Complete for activities from the target schedule. I’m trying to do it in gantt chart view, and then summarise.

Is there an easy way?

Replies

Gavin Morris
User offline. Last seen 15 years 16 weeks ago. Offline
Joined: 11 Jan 2005
Posts: 6
Thanks Paul, that’ll do for me. Easy when you know how ... :)

Paul Harris
User offline. Last seen 1 year 48 weeks ago. Offline
Joined: 11 Apr 2001
Posts: 618
I usually autostatus using progress spotlight a copy of the baseline and set it as Target 2. The % complete of this schedule will be the planned % complete.

Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers, Consulting and Training
www.eh.com.au


Paul Harris
User offline. Last seen 1 year 48 weeks ago. Offline
Joined: 11 Apr 2001
Posts: 618
I usually autostatus using progress spotlight a copy of the baseline and set it as Target 2. The % complete of this schedule will be the planned % complete.

Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers, Consulting and Training
www.eh.com.au