Dear all,
Pls inform me if there is any way to track productivity rates in P3. I m using excel sheet for this so far. For each activity in schedule, i get earned manhour vales from P3 based on percentage complete. and i input this to excel sheet on the related activity column. Actual manhours are coming from site timekeeper to whom i declared all activities and their descriptions. so i can calculate productivity rate with the ratio of actual manhours to earned manhours.
As far as i know, there is no problem to calculate earned value when i input percentage complete, P3 automatically calculates, but as for the actual manhour there is the only way to get this infrmation is site timekeeper.
But the point is can i input actual manhours to P3, and does it calculate the ratio between earned manhour and actual manhour.