Pacifico Pallasigui
User offline. Last seen 12 years 26 weeks ago. Offline
Joined: 24 Jan 2004
Posts: 62
Groups: None
Planners,

We already established a Baseline Target with resource and cost loaded and established a cash flow it is already approve by client.

This arabic consultant admised me to changed the actual quantity resource based on actual condition at site but my worry is we already established a baseline cashflow from which quantity is related to cost. Is this possible show in a report or layoutto change the actual quantity with without changing my baseline.

Thanks

Jun

Replies

Shah. HB
User offline. Last seen 50 weeks 1 day ago. Offline
Joined: 25 Nov 2008
Posts: 773
You can do it with the help of custom data items and global change
1 . Use custom data item select activity tab and assign AQ and character as precision
2. Use global change and select the resource whose BQ to be changed and apply conditions as shown
If RES EQ ENG
THEN AQ EQ BQ * 1.1 (any Multiplier to reflect your need )

I hope you can use these value in report it will not affect your baseline what ever you do in custom item and storing it in custom data will not affect your schedule