Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

S Curve Manhour- Baseline , Actual , Forecast

5 replies [Last post]
Jithin Kambhikanam
User offline. Last seen 2 weeks 2 days ago. Offline

Hello Everyone,

 

I would like to make a S Curve in Primavera which shows Planned, Actual and Forecast S Curve.

The basis of S Curve to be manhours / Week.

Can S Curve in Primavera show % Planned per week as Lables like in Excel.

I want to calculate the S Curve which shows end of the Week Palnned % and Actuals (Not start)

Please guide me.

 

Regards

Jithin

Replies

Zoltan Palffy
User offline. Last seen 25 weeks 2 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

NOTHING show the label you did not ask for the label 

Jithin Kambhikanam
User offline. Last seen 2 weeks 2 days ago. Offline

Hi Zoltan,

But that doesnt show % Planned Label per Week. 

 

It shows the curve but doesnt show the label.

Regards

Jitin 

Zoltan Palffy
User offline. Last seen 25 weeks 2 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

create a resource

assign the resource to the activities

assign the proper manhours to each activity

view show on bottom resource usage spreadsheet

Jithin Kambhikanam
User offline. Last seen 2 weeks 2 days ago. Offline

Hi Zoltan,

 

I am looking for a s curve which would be like this showing lables.

 

7355
capture.jpg

Zoltan Palffy
User offline. Last seen 25 weeks 2 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

create a resource

assign the resource to the activities

assign the proper manhours to each activity

view show on bottom resource usage profile

select the cureves that you want to show