2 replies [Last post]
Zameer Jeff
User offline. Last seen 2 years 44 weeks ago. Offline
Joined: 10 May 2007
Posts: 18
Groups: None
Hello friends
I have an activity which is looped in my project software 3.0. Please let me know how to get loop activity report to detect activity and get rid of loop.

Thanks

Replies

Zameer Jeff
User offline. Last seen 2 years 44 weeks ago. Offline
Joined: 10 May 2007
Posts: 18
Groups: None
Thank you very much Bradley. I got it.

Bless you
Regards
Zameer
Brad Lord
User offline. Last seen 10 years 22 weeks ago. Offline
Joined: 27 May 2003
Posts: 256
Groups: None
go tools, schedule and pick schedule reports, recalculate and it will give you a report which will show the Loop activities

regards

bradley