Adding Ramzan (Hourly) calender into P3

6 replies [Last post]
A D
User offline. Last seen 4 years 2 weeks ago. Offline
Joined: 20 May 2007
Posts: 1027
Hi,

I have prepared a schedule for 30 months with planning unit as DAYS. Now, i have been instructed by my PM to consider only 4 working hours during the ramzan month (4 weeks) against 8 hours during rest of the period.

In these four weeks, productivity for most of the items will be reduced by half.

So, can I add one more calender as planning Unit - HOUR, when i have already allocated calender with planning unit as DAY.

Any advise?

Raviraj

Replies

Ashraf Jahangeer
User offline. Last seen 8 years 37 weeks ago. Offline
Joined: 8 May 2007
Posts: 144
Hi Alex,

You are very correct if the total duration is in weeks then we should plan in hours e.g.shutdowns etc.


Regards,

Ashraf
A D
User offline. Last seen 4 years 2 weeks ago. Offline
Joined: 20 May 2007
Posts: 1027
Thanks Ashraf for the immediate response given.

This doesn’t work, but yaa as alex said i have to show every alternate day in ramdan month as non-working, which is not correct logically, but thats the only solution.

Cheers,

Raviraj
Ashraf Jahangeer
User offline. Last seen 8 years 37 weeks ago. Offline
Joined: 8 May 2007
Posts: 144
Hi Alex/Ravi,

Have you tried copying this project with HOURS as planning unit. I hope if it works the solution will be much simple.


Regards,

Ashraf
Ashraf Jahangeer
User offline. Last seen 8 years 37 weeks ago. Offline
Joined: 8 May 2007
Posts: 144
Hi Ravi,

The answer to your question is NO you cannot add one more calender as planning Unit - HOUR, when you have already allocated calender with planning unit as DAY.


You can try making a Calendar with equivalent working days (3 instead of 6). This may help to some extent.

Regards,

Ashraf