Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

P6 Calender Time Periods for Different Work Hours

2 replies [Last post]
Sreehari Eswarama...
User offline. Last seen 8 years 2 weeks ago. Offline
Joined: 30 Sep 2015
Posts: 2
Groups: None

I want to make 3 different calanders for a project which needs to be 8hrs/5day working, 12 Hrs/6day working and 24hrs/7day working. In the "Time Periods" section of each calander what values i should use for Hours/Day, Hours/Week, Hours/Month and Hours/year for each calendar? In the Global calader available on our system it is showning same values for all type of calenders. Is this the correct approch? 

4518
p6.jpg

Replies

Zoltan Palffy
User offline. Last seen 3 weeks 6 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

leave this setting as is only change the calendar 

Zoltan Palffy
User offline. Last seen 3 weeks 6 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

leave this setting as is only change the calendar