target bar doesn’t freeze

4 replies [Last post]
Luca Meli
User offline. Last seen 20 years 6 days ago. Offline
Joined: 10 May 2005
Posts: 6
Hello Guys

Today I copied my project and set the copied one as a target.

Now, when I compare the schedule with the target in the bar chart, what happens is that every time I change the remaining duration on my schedule it takes effect also on the target bar. If for instance I update the schedule and the remaining duration became less then the Original Duration then the schedule bar become shorter (fair enought) but what happens is that even the target bar get shorter following the schedule bar.

Looking at the P3 example it doesn’t happen. The target bar remain what it was fixed to be and the target ES and target EF do not change at all.

Should I check some rule to freeze my target bar?

Thanks
L.

Replies

Philip Jonker
User offline. Last seen 16 years 23 weeks ago. Offline
Joined: 7 Nov 2004
Posts: 852
Groups: None
It is because he had early dates specified for the target bar, and not the target dates.
Anand Kulkarni
User offline. Last seen 12 years 43 weeks ago. Offline
Joined: 4 Apr 2005
Posts: 41
Groups: None
Philip,

Is it a problem due to not saving as target project while the project is open?

Just for my understanding.
Luca Meli
User offline. Last seen 20 years 6 days ago. Offline
Joined: 10 May 2005
Posts: 6
Thanks Philip

It solved my problem.

Grazie
L.
Philip Jonker
User offline. Last seen 16 years 23 weeks ago. Offline
Joined: 7 Nov 2004
Posts: 852
Groups: None
The problem is probanbly, that when you created the target bar you did not set the required dates ti target 1 or 2 dates. Rightclick on the barchart area, then on Bars..., then on the target bar, and then on modify. Check under type that you have sppecified target 1 early start and finish.

Hope this helps