Planned % comp based on Late dates.

7 replies [Last post]
Muhammad Ali
User offline. Last seen 13 weeks 3 days ago. Offline
Joined: 25 Aug 2004
Posts: 18
Groups: None
Friends!

I am monitoring progress based on “Duration”. I want to draw a set of S curves in X-cel (Early and Late) for the planned progress % comp based on duration.

To get early planned % comp > I use Automatic update (Control F9) run the progress on weekly basis (repeatedly). The program activities are run on all early dates and summarization based on duration gives me overall planned % comp.

Coming to the exact querry. . Is there any way to get planned Late % comp. Like any option which makes Automatic update to start all the activities on their late dates, so that I can have planned Late % comp. !!

Thanx

Replies

Muhammad Ali
User offline. Last seen 13 weeks 3 days ago. Offline
Joined: 25 Aug 2004
Posts: 18
Groups: None
Daya I agree with you. Thanx Eric for you tip!! It really worked . .
Dayanidhi Dhandapany
User offline. Last seen 3 years 35 weeks ago. Offline
Joined: 18 Mar 2003
Posts: 470
Groups: None
Follow Erik’s advice; it would be easier to introduce a dummy resource to accomplish your task.

Erik Jonker
User offline. Last seen 5 years 30 weeks ago. Offline
Joined: 19 Apr 2003
Posts: 86
Groups: None
Hi Muhammad,

The only way to do this would be to create a duration resource.

The easiest way would be to add a resource called time and set the budget quantity equal to the original duration.

You would then be able to do an s-curve.

Regards,

Erik
Muhammad Ali
User offline. Last seen 13 weeks 3 days ago. Offline
Joined: 25 Aug 2004
Posts: 18
Groups: None
What I understand is that in Tools > Tabular or graphical reports, all reports are based on either cost or quantity.

Assume that my schedule is not cost or resource (Qty) loaded. I can not use any tabluar or graphical report!! My schedule contains only activities and I want to develop Early and Late S curves for the planned % comp.

My progress measurment will only be based on Tools > Options > Summarization > Duration.

May be I was unable to explain my querry properly.
Jaco Stadler
User offline. Last seen 18 years 6 weeks ago. Offline
Joined: 8 Sep 2004
Posts: 299
Groups: None
The Easy Way is to export the summary the report I found the easiast is Tools / Tabluar Report / Tabular / RT1.

You modify this report (Or copy) Then you Export You Can Select Which Dates you want to export on this (Timescale)

Hope this help
Muhammad Ali
User offline. Last seen 13 weeks 3 days ago. Offline
Joined: 25 Aug 2004
Posts: 18
Groups: None
Well, as long as I am able to get the data (could be a column inside the P3 schedule) I can export it to Xcel. My objective is to get % late comp for each activity that can be summarized to an overall % comp. . . .
Jaco Stadler
User offline. Last seen 18 years 6 weeks ago. Offline
Joined: 8 Sep 2004
Posts: 299
Groups: None
Do you want to show the percentage in a Column on the schedule or on the S-Curve