dennis walker
User offline. Last seen 20 years 1 week ago. Offline
Joined: 29 Apr 2004
Posts: 8
could anyone please explain how i can import an excel spredsheet into P3 the spreadsheet is created from MS Project
thanks for your help

Replies

MK TSE
User offline. Last seen 4 years 37 weeks ago. Offline
Joined: 27 Feb 2002
Posts: 550
Groups: None
As we have stated in previous posts, if the Project file is in .MPP (Project 2000 or later version), you need a MPP to MPX convertor to prepare a .MPX from .MPP

Once you have the .MPX, P3 will ’take’ the file by MPX to P3 conversion utility.
Vishwas Bindigana...
User offline. Last seen 49 weeks 2 days ago. Offline
Joined: 24 Apr 2004
Posts: 97
Groups: None
Hi,

I’m facing the same probs here. I have created a Project in MS Projects 2003. I cannot convert it using MPX-to-P3 conversion utility. Also, even if this happens partially, I loose all resouces, cash-flow, etc.

Any help would be appreciated.
Dayanidhi Dhandapany
User offline. Last seen 3 years 46 weeks ago. Offline
Joined: 18 Mar 2003
Posts: 470
Groups: None
Hello Karo,

what i understand from your question is you are able to convert MSP 98 to P3, but you can’t do it with MSP 2000 file then save MSP2000 file into lower version i.e, MSP 98 version file, then you can convert this file into P3.

or else you have to download the utility(MPP to MPX) converter file from primavera knowledge base to do the conversion of MSP 2000 file format directly into MPX file, then go to tools from p3, click MPX conversion utility, then select the MPX file to convert it into P3 files.

refer this link for further details

Regards

Daya
karo, kerry ugen
User offline. Last seen 18 years 4 weeks ago. Offline
Joined: 19 Nov 2002
Posts: 4
Groups: None
Good day,

Please can anyone tell me how possible for one to convrt from Microsoft project 2000 to P3, i can convert from Microsoft project 98 to P3, but with MP 98 icant.

can anyone help, please advice

kerry
MK TSE
User offline. Last seen 4 years 37 weeks ago. Offline
Joined: 27 Feb 2002
Posts: 550
Groups: None
If the MsProject is version 2000 or above, the file is in MPP format, then you need a MPP to MPX convertor for the changes. P3 default CD provide MPX to P3 function only.
MPP to MPX convertor is available on Primavera Knowledgebase.
Paul Harris
User offline. Last seen 1 year 47 weeks ago. Offline
Joined: 11 Apr 2001
Posts: 618
Dennis

There is a technical article about converting from MSP to P3 on my web site.

Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Book Publishers, Training & Consulting
www.eh.com.au
Dayanidhi Dhandapany
User offline. Last seen 3 years 46 weeks ago. Offline
Joined: 18 Mar 2003
Posts: 470
Groups: None
As a small suggestion, while if you want to import a big file of having more than 2000 lines, it is better to use .dbf as a file format, so that the import will be clean and perfect.
Marc Borburgh
User offline. Last seen 11 years 18 weeks ago. Offline
Joined: 22 Apr 2004
Posts: 55
First off ... there are a lot of topics in the forum about this that explain the ways to import. But hey ... try this:

1) Make an export to .wk1 from P3 with all the fields you will be filling from your MS Project Spreadsheet. In selection, select one (1) activity.

2) Open the .wk1 file in Excell and delete the exported row

3) Open the other spreadsheet too.

4) Copy/Paste the data (not the column names) from the Projects Spreadsheet into the P3 Spreadsheet in the appropriate columns

5) Save the .wk1 as a .wk1 file

6) Import the newly populated P3 spreadsheet into you planning

This should do the trick.
Last note ... always wise to backup your project prior to importing.