Suspension Dates on P3

8 replies [Last post]
Forum Guest
User offline. Last seen 17 weeks 6 days ago. Offline
Joined: 28 Jan 2009
Posts: 2
Groups: None
Dear Experts,

Suspension Dates for some projects occurs more than once...maybe twice or more...

But in P3, i think it can only be recorded once (am i right?)...how would you deal with it when the project have some suspension more than once?

Hope to solve this kind of problem..

Thanks alot

Alfon
SCDC

Replies

A D
User offline. Last seen 4 years 2 weeks ago. Offline
Joined: 20 May 2007
Posts: 1027
Go to Bars and make sure NECK is under visible mode.

If neck is unchecked, then it will show a straight bar.

Cheers,

Rav
Gayantha Abeywardena
User offline. Last seen 11 years 48 weeks ago. Offline
Joined: 27 Feb 2008
Posts: 41
Groups: None
Hi Rav

I followed your steps but no changes in the bar how does it appears????? will version 5 helps ....

GA
A D
User offline. Last seen 4 years 2 weeks ago. Offline
Joined: 20 May 2007
Posts: 1027
you can show suspended activities by pressing F7 --> DATES Tab --> Suspend date and resume date

We cannot show suspension activities in baseline program. In updated program, it must have actual date.

But, activity suspension for four times......? I dont think so, its possible in P3. You can show it only once, I believe.

Cheers,

Rav
Gayantha Abeywardena
User offline. Last seen 11 years 48 weeks ago. Offline
Joined: 27 Feb 2008
Posts: 41
Groups: None

Dear All,
I want to show the suspension of activity four times due to obstructions. as we are using P3 please tell me a way to show this in a program its single activity (placing conduite)

GA
Alfon Lyndon Joson
User offline. Last seen 7 years 36 weeks ago. Offline
Joined: 28 Mar 2004
Posts: 35
Groups: None
tx alot guys and best regards....


ALFON
SCDC
Luca Basile
User offline. Last seen 9 years 42 weeks ago. Offline
Joined: 10 Jul 2003
Posts: 288
Groups: TILOS
I am agree with Choi, is not that You have to put several suspension and resume because Your schedule is to high level?
If not split down it in any case in different activities, put before a milestone with an "self explaning" start milestone taht will help You later on in the possible preparation of the claim.
To group the activities resulting from this splitting use the coding structure.
When You just put suspend and resume you loose the reason, I prefer to split and put self explaining milestone.
Forum Guest
User offline. Last seen 17 weeks 6 days ago. Offline
Joined: 28 Jan 2009
Posts: 2
Groups: None
You should be seperately recording each and every occasion where for no fault of your own you are unable to proceed.

This gives a full record of interruptions to the work and is invaluable if you needed to prepare a claim.
clarence choi
User offline. Last seen 13 years 14 weeks ago. Offline
Joined: 27 Feb 2004
Posts: 6
Groups: None
I believe your down times should have reasons for that.
Options:
1. sub-divide your activity into avtivities.
2. create a new calendar and assign the down time as non-working dates in the calendar.
Hope this will help.