Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Activity Suspension

4 replies [Last post]
Adnan Amjad
User offline. Last seen 18 years 48 weeks ago. Offline
Joined: 10 May 2005
Posts: 8
Groups: None
I want to show the suspension on activity due to rain more than once in a week but in P3 u can show suspension of an activity only once have anyone got the solution.

Replies

Mike Testro
User offline. Last seen 36 weeks 16 hours ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi David

Put it on the calendar as non work days.

Best regards

Mike T.

David Burrows
User offline. Last seen 8 years 29 weeks ago. Offline
Joined: 12 Oct 2006
Posts: 5
Groups: None

I have a project that has 3 periods of total suspension that needs to be built into the schedule.  

Each period will be for a minimum of 14 days and while the suspendion of work is known ahead of time, the project period does not include the 42 days involved.  

Is there a way to show the planned 14 day work suspensions without the time accruing against the total project time? 

 

THANK YOU FOR YOUR ASSITANCE. 

 

David R Burrows

Steven Oliver
User offline. Last seen 12 years 1 week ago. Offline
Joined: 8 Nov 2002
Posts: 313
Groups: None
If you have a need to retain the information, I would suggest that the most effective method would be to add new activities to describe the delay. In this way demonstration of the effect is much clearer and easily understood.

HTH
Adnan Amjad
User offline. Last seen 18 years 48 weeks ago. Offline
Joined: 10 May 2005
Posts: 8
Groups: None
Right, for rainy days Calander holidays are most effective but if suspension is for any other reson effecting only that perticular activity more than once then is there any other alternative available then defining a new separate calander for that perticular activity.
Paul Silver
User offline. Last seen 5 years 36 weeks ago. Offline
Joined: 30 Sep 2004
Posts: 16
Adnan,

Consider modifying your calendar to reflect the rain days.

Regards
Paul Silver