Activity Suspension

7 replies [Last post]
Abilash Palakkada...
User offline. Last seen 9 years 3 weeks ago. Offline
Joined: 25 Aug 2012
Posts: 47
Hi guys, In P6 8.1, I found something strange with activity suspension; when I have updated the schedule with DD – 14/Feb/14 I found one activity to be suspended from 28/Feb/14 till 15/Mar/14. After entering the suspension and resume dates, when I reschedule the activity moves and it shows that the remaining job to be performed only after 15/Mar/14 onwards. It doesn’t shows the work to be performed between data date and suspension date (14/Feb/14 ~ 28/Feb14). This is affecting the resource distribution as well; have any of you experienced this? Advise if you have any suggestions to fix / get rid-off this problem. Regards, Abilash

Replies

Tom Reichner
User offline. Last seen 6 years 8 weeks ago. Offline
Joined: 23 Nov 2011
Posts: 46

For the suspend-resume activity, keep following the predecessors back until you find a relationship that eliminates the suspend-resume situation when you change the relationship. The newer versions of Primavera seem to be more sensitive to continuity of the start-finish relationships in a path. 

Ravi Katare
User offline. Last seen 10 years 30 weeks ago. Offline
Joined: 14 Jul 2014
Posts: 23
Groups: None

Hi Abhi,

- If the suspend/resume functionality is used then the early start is set equal to the resume date, its design for work in this     way only .

Also you should know; - The early finish is calculated using the resume date and the remaining duration.- If the suspend date is entered without a resume date then, P6 ignores the suspend date.- Units and costs are not spread over the period of suspension.- P6 calculates an actual duration for all activities based on the amount of non-suspended time.- The amount of time that an activity’s progress is suspended is generally deducted from the total duration. - Ravi
Nima Sadeghi
User offline. Last seen 10 years 39 weeks ago. Offline
Joined: 13 May 2014
Posts: 2
Groups: None

Hi Abilash / Mike,

 I'm also experiencing the same issue! I checked all the settings and calendars and it still shows inactive period between the datadate and suspend date. Is yours resolved or you still have the problem? Please help / advise.

 

Regards, Nima 

Abilash Palakkada...
User offline. Last seen 9 years 3 weeks ago. Offline
Joined: 25 Aug 2012
Posts: 47
Hi Khaja, There is no constraints or any driving relationships. Br Abilash
Khaja Sharief
User offline. Last seen 11 years 1 day ago. Offline
Joined: 9 Sep 2008
Posts: 44

Please check if there any constraints imposed and activity relationships.

Abilash Palakkada...
User offline. Last seen 9 years 3 weeks ago. Offline
Joined: 25 Aug 2012
Posts: 47

Hi Mike, Both calendars are active during 14/Feb/14 ` 28/Feb/14

 

Br,

Abilash

Mike Testro
User offline. Last seen 11 weeks 5 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Abilash

Check your calendars both on the task and resource allocations.

Best regards

Mike Testro