% Complete difference

3 replies [Last post]
Jerome Odeh
User offline. Last seen 9 hours 53 min ago. Offline
Joined: 19 Jan 2004
Posts: 105
In my schedule, the % Complete weighting is based on Cost(Tools>Option>Summarisation) and when I run the schedule it shows 50% Complete. But when I read the Scheduling Report produced in Primavera Look, it showed 48.9% complete.

Interesting, if I change the % Complete weighting to Duration, my schedule shows 49% which tallies with Primavera Look Report’s 48.9%.

How can I get the Scheduling Report generated in Primavera Look to also calculate & display % Complete based on Cost like my schedule?

Replies

Jerome Odeh
User offline. Last seen 9 hours 53 min ago. Offline
Joined: 19 Jan 2004
Posts: 105
Thanks Dgd.........I just ran a detailed Cost Report from Tools>Tabular Reports>Cost>Control and it painted the picture I wanted to see.......


And to Harris...I’ve been using your P3 book since december and I’ve found it invaluable......thanks.
Jerome Odeh
User offline. Last seen 9 hours 53 min ago. Offline
Joined: 19 Jan 2004
Posts: 105
Thanks the replies but my question is all about the Schedule Command Report.

I’d like the Schedule Command Report % Complete to be same with the Project % Complete displayed on the % column when % complete weighting is based on cost and not duration.

For now, I’m disregarding it like Dgd suggested but I’m a bit curious about this.
Paul Harris
User offline. Last seen 1 year 35 weeks ago. Offline
Joined: 11 Apr 2001
Posts: 618
The help file states that the Schedule report is summarized using the options selected in Tools, Schedule, Options, Summarization, so in theory you are doing the correct thing.

I have found in the past to make one report run correctly I had to recalculate twice! I do not recall which.

You may wish to take this issue up with Primavera technical support, but I feel you are doing the correct thing.

You may wish to create a new schedule with say two or three activities, where it would be simple to calculate the results by manually, and check if the report still runs incorrectly.

Paul E Harris
Eastwood Harris Pty Ltd
Planning and Scheduling Book Publishers